Pull Planning for Small Contractors: Build the Phase Plan Backward From the Milestone

Zace Team 4 min read

Cover: pull planning, start at the milestone, with the Zace logo

Most small contractors plan forward. Framing starts Monday, drywall in three weeks, paint after that. Then handover arrives and nobody can say which trade ate the slack.

Pull planning flips it. Start at the milestone you promised and ask, step by step, what has to finish before this can start, and who does it. And you ask the people who will do the work.

Sign up free

What pull planning is, and what it is not

Pull planning is the phase planning step of the Last Planner System. It takes one chunk of the job between two milestones and works out the handoffs. Each handoff is a promise between two crews: the tiler asks when the floor drains will be set, and the plumber gives a date he will stand behind.

It does not replace your master schedule. The master still carries the contract dates and the overall sequence, as we covered in master schedule vs lookahead. A pull plan usually details one phase of about six to twelve weeks of work (per the schedule.construction pull planning guide).

Before the session

Pick one milestone that ends a phase and that everyone understands. "Kitchen ready for cabinets" works. "Phase 2 done" does not, because each trade reads it differently.

Invite the foremen and lead hands who run the crews, subs included. If a trade is missing, someone else guesses its work, and you are back to a push schedule. Ask each lead to bring their tasks and durations for the crew they actually have.

Running the session

Book two to three hours for one phase. Past that, people start agreeing just to leave. Sticky notes, a whiteboard or a shared screen all work, as long as each lead writes their own tasks.

Procore's pull planning guide describes the same flow, with each constraint logged against an owner and a date.

Turn the needs into a constraint list

Every "I need" note from the session is a constraint. Give each one a name and a due date before people leave. A fixture with a four week lead time is the office's job this week, not the electrician's problem on week five.

Weather belongs on that list too. If an exterior phase runs through the rainy months or peak summer heat, mark the days you expect to lose. Our guide to planning weather delays into the schedule shows how.

Feed the plan into the lookahead and the weekly score

A pull plan left on a wall photo dies by Friday. Within a day or two, put the tasks, durations, handoffs and owners into the schedule. If the session showed a duration in the master was wrong, fix the master and flag the milestone if it is at risk.

As the phase gets close, its tasks roll into your 3-week lookahead, where you clear the constraints before the week arrives. Each week crews commit to ready tasks, and you count how many got done. That count is your Percent Plan Complete score, and it shows whether the promises made in the session were real.

Putting it on one plan

After the session, set the milestone in the plan and link each task to the one it hands off to with a dependency. If the plumber slips two days, everyone after him sees it on the Gantt chart. Assign every task to the lead who committed to it, and let the crews open the same plan on their phones.

Zace gives you milestones, task dependencies, Gantt charts and task assignment, on web, Android and iOS, so the plan your foremen built is the same one the office tracks.

Frequently asked questions

What is pull planning in construction?

Pull planning is a way to schedule a phase of work by starting at a milestone and working backward. The crews who will do the work agree on each handoff and list what they need before they can start.

How long should a pull planning session take?

Plan for two to three hours to pull plan one phase. Longer sessions tend to lose focus, so split a big job into several phases and run one session for each.

Does pull planning replace the master schedule?

No. The master schedule keeps the contract dates and the overall sequence. A pull plan details one phase, and what it learns about durations and handoffs should be fed back into the master and into your lookahead.

Start at the date you promised, let the crews pull the work back to today, and the plan they build is the one they will work to.